  • At least at the start of June, Metra will continue operating the current alternate weekday schedules on all lines. Most Metra lines operating weekend service (except the Metra Electric) have temporarily changed to Sunday schedules for both Saturday and Sunday service. Saturday service on Metra’s SouthWest Service Line is suspended until further notice. The Metra Electric Line will continue to operate Saturday schedules on Saturdays and Sunday schedules on Sunday.
  • Metra is launching a new $10 All-Day Pass on June 1 and strongly encouraging customers to buy it in the Ventra app, giving them a “Touch Less, Pay Less” option to ride its trains safely and affordably. Click here for details.
  • For more information about Metra's COVID-19 response and service, please go to our update page.
Last Updated - 05/28/2020 - 3:49PM

Metra gets state funding for two new stations

(April 17, 2019) - 

Metra today added funding for two new stations In Chicago to its capital program after the state of Illinois said it would release the money for the long-awaited projects. The stations will be built at Auburn Park near 79th Street on the Rock Island Line and Peterson and Ridge on the Union Pacific North Line.

The two stations have been planned for years, and Metra intended to fund construction of both with its share of proceeds from two state of Illinois bond programs from 2009. However, that funding was first held up in the state’s budget woes and then cut in 2017, when the state informed Metra that its share from the bond programs would be reduced to $835.7 million from $1.1 billion.  

Funding for the stations was restored in recent state budgets, and the state has told Metra it is releasing the money – $15 million for Peterson Ridge and $20 million for Auburn Park.

Planning for the Peterson Ridge Station is further along than for Auburn Park, with the engineering design essentially complete. Metra anticipates putting the project out to bid this summer with construction starting later this year or early next year.

Work on the design for the Auburn Park Station is currently 60 percent complete. The Metra Board today approved a $1.1 million change order with the firm T.Y. Lin International, Inc., to complete design for the station to be located just south of 79th Street on the Rock Island Line. Metra’s goal is to have the design complete by the end of 2019 with construction planned for spring 2020.

 