Major Improvements on the Union Pacific North Line

(July 16, 2010) - 
Work will begin in August 2010 on a $185M bridge and retaining wall construction project on the Union Pacific North Line. A total of 22 bridges on the north side of Chicago will be replaced, with the construction split into two phases. During the first phase of the project, 11 bridges will be replaced between Grace Avenue and Balmoral Street. In the second phase, 11 more bridges between Fullerton Avenue and Cornelia Street will be replaced.
 
The project is expected to be completed at the end of 2018.
 
There will be no disruption of service at any of the Union Pacific North Line stations during construction. There will be minor adjustments to the train schedules and travel times will stay the same as the current schedule or increase by a few minutes. The changes in schedule will be effective August 22, 2010.
 
For the final schedule, please see this document.
 
There will be three Union Pacific North Line bridge open house forums at the following times and locations:
 
Thursday, July 29th, 5:00 PM - 7:00PM
Waukegan City Hall
Board Room
100 N. Martin Luther King Jr. Avenue
Waukegan, Illinois
 
Monday, August 2nd, 5:00 PM - 7:00 PM
Lake Forest City Hall
220 East Deerpath Road
Lake Forest, Illinois
 
Wednesday, August 4th, 5:00 PM - 7:00 PM
Evanston Public Library
Community Room
1703 Orrington Avenue
Evanston, Illinois