Edgebrook Station

/content/metra/en/home/about_metra/capitalprojects/construction_projectupdates/Edgebrook_Station/jcr:content/mainPar/textimage/image/file

District/Line:

Milwaukee North

Location(s):

Edgebrook Station

Type:

Platform Replacement


Project Description:

This project consists of replacing the inbound and outbound platforms and installing lighting on the inbound side.

Beginning Tuesday May 1, 2012, and continuing for approximately 5 months, the outbound platform at Edgebrook will be rehabilitated.  The outbound platform will be closed off in sections to allow for train boarding.  Work will begin on the north half of the outbound platform.  Parking spaces #101 to #127 may be removed from service to accommodate this work.

Project Start Date: May 2011
Anticipated Completion Date: 2012
Percentage Completed: 50%